Construction bids for Loudoun County's Route 15 North widening are due by 4 p.m. on Friday, November 20. The county's own schedule targets substantial completion for spring 2030. If you're weighing a home in Selma Estates, Beacon Hill, Saddlebrook or Raspberry Falls this winter, the four-lane road is where the project ends. A purchase made in 2026 or 2027 lives through the years before it: tree work, utility relocation, right-of-way acquisition and roadwork, staged one stretch at a time.
The county's schedule does not reach every stretch at the same time. The work moves along the corridor in segments, and the middle stretch comes last. Two homes a mile apart on Route 15 can sit next to active work in different years. For a buyer comparing this corridor with in-town Leesburg or Lansdowne, location on the corridor matters more than the finished road.
Where Four Lanes Become Two
The project starts at Battlefield Parkway, where Route 15 currently narrows from four lanes to two. It runs about 3.5 miles north to Montresor Road and widens that stretch to two lanes in each direction. It is paid for with local and regional Northern Virginia Transportation Authority funds. The plans were drawn in three phases. Phase I runs from Battlefield Parkway to Whites Ferry Road. Phase IA covers roughly 2,000 feet north of Whites Ferry Road. Phase II runs from there to Montresor Road.
The county's invitation for bid lists the limits on construction plainly: overhead and underground power and communication lines, karst and limestone geology, the existing floodplain, private properties next to the road, and connections to local roads and driveways. Every driveway and side road that meets this stretch of Route 15 has to be tied into the new road, and that takes time.
The Finish Date Has Already Moved
The spring 2030 date is the latest of several. Loudoun's FY2025 adopted capital improvement program put completion of the Whites Ferry Road to Montresor Road segment in FY2029. The county later regrouped the project's segments, so the two estimates don't cover exactly the same stretch. In its status report dated April 17, 2026, the NVTA said construction would start five months late and moved the overall project completion date from December 30, 2028, to November 1, 2030.
The county's bid document calls its milestone dates "for reference only and subject to change." Within about two years, the expected finish has moved from late 2028 to 2030. A buyer closing this winter should plan for the construction years as part of owning the home, and should expect the 2030 date to keep moving if the schedule does.
Which Stretch Gets Its Turn When
The county's schedule sets the order of the work. Utility relocation is the part that reaches each stretch at a different time:
| Milestone | Stretch of Route 15 | County's scheduled window |
|---|---|---|
| Design approval from VDOT and Town of Leesburg | Whole project | Fall 2026 |
| Environmental permits | Whole project | Fall 2026 |
| Right-of-way acquisition complete | Whole project | Winter 2027 |
| Utility relocation | Battlefield Parkway to Saddlebrook Place | Summer 2026 to winter 2027 |
| Utility relocation | Station 472+00 to Montresor Road | Spring 2027 to winter 2028 |
| Utility relocation | Saddlebrook Place to Station 472+00 | Spring 2028 to winter 2029 |
| Substantial completion | Whole project | Spring 2030 |
Station 472+00 is a survey marker a little past the Phase IA endpoint, which sits about 2,000 feet north of Whites Ferry Road. In plain terms, the south end near Battlefield Parkway goes first, the north end toward Montresor Road goes second, and the stretch from Saddlebrook Place past Whites Ferry Road goes last, with work scheduled into winter 2029. Utility work will overlap with construction, and the segments are staggered so they don't conflict with each other. The longer lines belong to Dominion Energy, Verizon, NOVEC Fiber Solutions, Zayo and Segra, and they move to the east side of the corridor. The contractor may also work at night under VDOT's Northern Virginia lane closure guidelines.
Work along the road has already been scheduled. In March, the county announced tree clearing between Battlefield Parkway and Whites Ferry Road to prepare for utility relocation. The announced window ran from the week of March 9 to mid-April 2026, with possible daytime flagging and temporary lane closures. Expect that kind of short-notice lane control off and on for several years, depending on the segment.
What the Finished Road Changes at Each Intersection
The finished design changes more than the lane count. Each change sits at a specific intersection, so it helps some homes on the corridor more than others.
At the south end, the North King Street intersection becomes a signalized Continuous Green T. Through traffic heading north on the Route 15 Bypass won't have to stop there. Whites Ferry Road gets an updated signal. In 2025, the county confirmed in a Q&A that the Raspberry Drive and Whites Ferry Road intersection, the one that serves Raspberry Falls, gets a signal, not a roundabout. At the north end, Montresor Road gets a two-lane hybrid roundabout, and a realigned piece of Limestone School Road will connect into it. Where Route 15 crosses Limestone Branch, the stream will be moved and the old culvert replaced with two parallel steel-girder bridges.
The project also adds a walking and biking route. A 16-foot regional trail will run from Tuscarora High School on North King Street to Whites Ferry Road, and a 10-foot shared-use path will continue from there to Montresor Road. Both run along the west side of the corridor. For homes in the northern subdivisions, that is a paved connection toward town on foot or by bike. That connection isn't there today.
Farther North, Two Crossings Are Still Undecided
Past Montresor Road, the corridor's two other big questions sit outside this project: the Lucketts bypass is still in the alignment stage, and White's Ferry has a new owner on the Maryland side but no service.
The first is Lucketts, a separate bypass project. At the county's June 2025 public meeting, the Stumptown Road and Lucketts Road signal was rated LOS F, the lowest level of service, during the morning peak. Southbound queues often ran longer than a mile, and side-street waits topped a minute. In a September 1 notice, the county announced a September 29 meeting on a proposed mini-bypass on the west side of Lucketts. As of November 1, the Loudoun Wildlife Conservancy reported that two concepts were still under consideration, the mini-bypass and a four-lane Alignment A. The Board of Supervisors is expected to pick an alignment in early 2027. Lucketts also has a new reason to stop. Northern Virginia Magazine reported that the Young Lucketts Vintage Store opened February 7 at 12810 James Monroe Highway with 18 local vendors.
The second is White's Ferry, at the end of Whites Ferry Road, which for a household with ties to Montgomery County is a direct crossing of the Potomac. On July 24, Montgomery County announced that it had completed the transfer of the ferry's Maryland property and business. Service won't resume until rights to the Virginia landing are restored, and the county did not give a reopening date. The Loudoun Times-Mirror reported that Catoctin District Supervisor Caleb Kershner was working with the parties toward a deal and did not believe a majority of the Board supported eminent domain. A home near Whites Ferry Road should be valued on today's routes. Any future ferry service is a possibility, not something you can count on.
Reading a Listing on This Corridor
Comparing a home here with one in town or in Lansdowne comes down to dates, and the county has published most of them. Start with where the subdivision's entrance meets Route 15. Then match that point to the table above to see which utility relocation window falls during your first years of ownership. A home whose entrance is near Battlefield Parkway gets its segment's utility work done first. A home off the stretch between Saddlebrook Place and Whites Ferry Road is scheduled for utility work through winter 2029.
Next, drive the route at the hours you'll actually use it, from the subdivision entrance to the point where Route 15 widens to four lanes at Battlefield Parkway. That drive is what you'd live with until spring 2030 at the earliest. If the property fronts Route 15, ask the county project team whether the parcel falls within the project's construction or utility easement areas before you write an offer. The bid document lists neighboring private properties and driveway tie-ins among the project's constraints.
Finally, think about when you might sell. If you might resell before 2030, your buyers will look at the same construction calendar. If you plan to stay through 2030, you're buying at today's two-lane conditions and holding into the finished four-lane road, the North King Street Continuous Green T and the trail. If you're also weighing a new build against an existing home in the area, our guide to choosing new construction or resale in Leesburg covers that decision, and our Leesburg neighborhood page covers the town side of the comparison.
Frequently Asked Questions
When is the Route 15 widening north of Leesburg expected to be finished? The county's bid document targets substantial completion for spring 2030. The NVTA's April 17, 2026, status report lists project completion as November 1, 2030, moved back from December 30, 2028.
Does the widening include the Lucketts bypass? No. The widening ends at Montresor Road. The Lucketts bypass is a separate project. As of November 1, two alignments were still under consideration, and a Board decision is expected in early 2027.
Is White's Ferry running? As of Montgomery County's July 24 announcement, service could not resume until rights to the Virginia landing were restored, and no reopening date had been set.
If a home on the Route 15 corridor is on your shortlist, Konah Real Estate Group can match its entrance to the county's construction schedule, drive the route with you at the hours you'll use it, and set your offer around the years until 2030. Schedule a consultation, and we'll go through the address with you before you commit.